How long is a building permit valid?

It is valid until 180 days past the issue date or the last approved inspection.

Show All Answers

1. What does not require a permit?
2. How do I apply for a building permit?
3. How do I pay for a permit?
4. Who can apply for a building permit?
5. Can I extend a building permit?
6. How long is a building permit valid?
7. What is the turnaround time after I submit a building permit application?
8. How do I get a driveway permit?
9. How do I schedule an inspection?
10. When will the building inspection be set?
11. Can I find out when during the day my building inspection will be done?
12. What codes are we using?
13. What is the wind speed design criteria in Sumter County?